Project Black Mountain Road – Landslide Remedial Works
Location Black Mountain QLD 4563
Client Noosa Shire Council
Key works Roadways, Flood mitigation
Status Current

The landslide, triggered by heavy rainfall in early 2022, spans over 130 meters in width, is as deep as a five-storey building, with a depth movement exceeding 15 meters. Geotechnical investigations confirm it as one of the most significant landslides impacting a road asset in the Noosa and Sunshine Coast region in the last 30 years. Extensive damage lies beneath the surface, requiring a careful restoration process.

Hazell Bros is over half-way through driving 266 steel-lined bored piles, each with a diameter of 900mm, to a depth of up to 25 meters. This includes the installation of some of the largest soil nails currently used in the southern hemisphere. The scale of the project requires an estimated use of 6,000 cubic meters of concrete, equivalent to two and a half Olympic-sized swimming pools, and 800 tonnes of steel.

The comprehensive remediation effort involves:

The recovery works are jointly funded by the Australian and Queensland Governments through the Disaster Recovery Funding Arrangements (DRFA).

ProjectRosebery Tailings Dam Upgrade
LocationRosebery
ClientMinerals and Metals Group (MMG)
StatusCompleted 2017

In 2016/17 Hazell Bros was engaged by MMG to upgrade the Rosebery Tailings Dam. Some of the works included:

Awarded the Tasmanian Civil Contractors Federation Earth Award in 2018 - Category 5 Project value between $30M and $75M.


ProjectConglomerate Dam Upgrade
LocationRosebery
ClientTasWater
StatusCompleted 2018

Built in 1971 of earth and rockfill construction, Conglomerate Dam has a storage capacity of 53.1ML. In 2017 Hazell Bros was engaged by TasWater to undertake an upgrade of the dam. Some of the works included:

2019 Cattle Hill Wind Farm (Goldwind)

This is the largest contract ever awarded to the business in its own right.

Works included 48 turbine footings, each averaging 450m3 of concrete; 26km of access roads; crushing and screening of road building material on site; steel fixing; management of 40km of electrical reticulation cabling; construction of substation, including control building; and operations and maintenance building.


2007 Studland Bay Wind Farm (Hydro Tasmania)

Works included construction of 24km access roads; establish and operate two mobile concrete batch plants to produce 15,000m3 of concrete; construction of 25 16.6x16.6m reinforced concrete footings for the towers, each containing 40T reinforcing steel and 450m3 concrete; construction of 25 45x45m hardstands; design and construction of control building; construction of switchyard footings; installation of 25km of underground cables; and civil works for 5km of transmission line, including temporary access roads and pole footings.


2012/13 Musselroe Wind Farm (Hydro Tasmania)

Works included construction of control building and associate switchyard footings; construction of 45km of internal road network and associated local road upgrades; construction of 56 octagonal reinforced concrete footings for the towers; onsite quarrying of road building materials; establishment and operation of two mobile concrete batch plants; and establishment of a fully-equipped 80-person construction camp in Gladstone.

LocationEast Devonport, TAS
ClientTasPorts
Key worksPorts & harbours
StatusCompleted 2024

The joint venture project delivered an upgrade of the existing Berth 3E to make it suitable for operation, including berthing, mooring and stern-loading of a roll-on roll-off (ro-ro) ship up to a length of 212m, for both passengers and freight between Geelong, VIC and Devonport (new Spirit of Tasmania vessels).

The scope of the works under the contract included:

The project adopted the use of 8T rock bags as scour protection in the berth in lieu of large rock and associated additional dredging. This is the first time in Australia that these rock bags have been used in this application. The bags are also made from recycled materials and are filled with rock from a local Hazell Bros quarry.

The wharf piles are coated with a 3-layer polyethylene (3LPE) coating system to increase the durability of the piled structure and lower life cycle costs for the asset owner.

Works have been carried out with strict environmental monitoring to ensure compliance to relevant water quality, turbidity, noise and dust standards. Site reuse of material has been maximised where possible with dredge rock and concrete demolition waste being crushed on site and reused in the reclamation areas.

Location Launceston, Tasmania
Client City of Launceston
Key works Other
Status Completed 2019

The project involved removal of the existing 20,200m² playing surface and reconstructing to a standardised 19,000m² oval to international standards. The construction process involved several distinct stages including:

  • Demolition and excavation of the exiting surface and boundary infrastructure
  • Subgrade stabilisation
  • Construction of the clay dome base
  • Installation of the irrigation system and communications infrastructure
  • Laying of Megaflo drainage pipe and spreading of the drainage aggregate
  • Spreading the rootzone sand and incorporating additives
  • Turf harvesting and installation; and
  • Boundary structure and LED panel installation.
Key Challenges
Subgrade stabilisation
The site was located on an historic tip site and subgrade level was within 200mm of the water table. The specified subgrade stabilisation method of cement/lime stabilisation was not practical in some of the softer areas due to the weight of the mixing plant potentially disturbing the ultra-soft subgrade. In these locations Hazell Bros stabilised the subgrade with a geo-grid layer and cement stabilised aggregate.
 
Sand compliance
One of the most critical parts of the project was ensuring the rootzone sand would meet the USGA specifications, especially around hydraulic conductivity. This required an extensive process of testing in all three phases:
  • preliminary testing of the proposed sand blends
  • production testing as suitable sands were stockpiled
  • testing during placement.
Timeframe
The timeframe was also extremely short – 18 weeks, August to December – with the ground needing to be handed back to give ground staff enough time to fine-tune the surface before its first BBL09 fixture on 30 December.

Hazell Bros completed the project on budget and two weeks ahead of programme. The quality of works surpassed UTAS Stadiums expectations and further enhanced the grounds reputation as an international standard, multi-use, sport playing surface.

The project was awarded the Engineers Australia: Australian Engineering Excellence Awards 2020 (TAS).
 
 
 
 

 

LocationLake King William, TAS
ClientHydro Tas
Key worksDams
StatusCurrent

The project involves construction of the intake excavation and downstream portal for the first stage of a new water conveyance directing water from Lake King William down to the Tarraleah Power Station. The 2 excavation sites will eventually be connected by a tunnel to allow the water to be piped through the surrounding mountains.

A plastic concrete cut-off and wave bund coffer dam were first constructed to protect the intake excavation from the rising lake levels and allow excavation to continue unimpeded. Excavation of ~130,000m3 of glacial soil and ~120,000m3 of dolerite rock is required at the intake site to reach the invert of the future tunnel.

Ground support is required to protect the steep excavation batters at both excavation sites, with a significant amount of rock bolts and shotcrete to be installed.
The project is due to be completed mid-2024.

LocationDon and Lower Barrington, TAS
ClientTasmanian Irrigation
Key worksPipelines
StatusCompleted 2023

The project involved laying of approximately 50km of distribution pipeline for two irrigation schemes; the Don Irrigation Scheme which draws water from the Forth River, and the Barrington Irrigation Scheme from Lake Barrington.

The pipeline was constructed with buttwelded 20m lengths of DN560 and smaller HDPE pipe.
The pipeline accessed 123 privately owned properties with 69 property outlets installed.

Installation of the pipeline encountered high production cropping farms, extreme wet weather, hard rock, and water, service and road crossings.

The project was completed in 14 months.

cross