2019 Cattle Hill Wind Farm (Goldwind)

This is the largest contract ever awarded to the business in its own right.

Works included 48 turbine footings, each averaging 450m3 of concrete; 26km of access roads; crushing and screening of road building material on site; steel fixing; management of 40km of electrical reticulation cabling; construction of substation, including control building; and operations and maintenance building.


2007 Studland Bay Wind Farm (Hydro Tasmania)

Works included construction of 24km access roads; establish and operate two mobile concrete batch plants to produce 15,000m3 of concrete; construction of 25 16.6x16.6m reinforced concrete footings for the towers, each containing 40T reinforcing steel and 450m3 concrete; construction of 25 45x45m hardstands; design and construction of control building; construction of switchyard footings; installation of 25km of underground cables; and civil works for 5km of transmission line, including temporary access roads and pole footings.


2012/13 Musselroe Wind Farm (Hydro Tasmania)

Works included construction of control building and associate switchyard footings; construction of 45km of internal road network and associated local road upgrades; construction of 56 octagonal reinforced concrete footings for the towers; onsite quarrying of road building materials; establishment and operation of two mobile concrete batch plants; and establishment of a fully-equipped 80-person construction camp in Gladstone.

LocationEast Devonport, TAS
ClientTasPorts
Key worksPorts & harbours
StatusCompleted 2024

The joint venture project delivered an upgrade of the existing Berth 3E to make it suitable for operation, including berthing, mooring and stern-loading of a roll-on roll-off (ro-ro) ship up to a length of 212m, for both passengers and freight between Geelong, VIC and Devonport (new Spirit of Tasmania vessels).

The scope of the works under the contract included:

The project adopted the use of 8T rock bags as scour protection in the berth in lieu of large rock and associated additional dredging. This is the first time in Australia that these rock bags have been used in this application. The bags are also made from recycled materials and are filled with rock from a local Hazell Bros quarry.

The wharf piles are coated with a 3-layer polyethylene (3LPE) coating system to increase the durability of the piled structure and lower life cycle costs for the asset owner.

Works have been carried out with strict environmental monitoring to ensure compliance to relevant water quality, turbidity, noise and dust standards. Site reuse of material has been maximised where possible with dredge rock and concrete demolition waste being crushed on site and reused in the reclamation areas.

LocationLake King William, TAS
ClientHydro Tas
Key worksDams
StatusCurrent

The project involves construction of the intake excavation and downstream portal for the first stage of a new water conveyance directing water from Lake King William down to the Tarraleah Power Station. The 2 excavation sites will eventually be connected by a tunnel to allow the water to be piped through the surrounding mountains.

A plastic concrete cut-off and wave bund coffer dam were first constructed to protect the intake excavation from the rising lake levels and allow excavation to continue unimpeded. Excavation of ~130,000m3 of glacial soil and ~120,000m3 of dolerite rock is required at the intake site to reach the invert of the future tunnel.

Ground support is required to protect the steep excavation batters at both excavation sites, with a significant amount of rock bolts and shotcrete to be installed.
The project is due to be completed mid-2024.

LocationDon and Lower Barrington, TAS
ClientTasmanian Irrigation
Key worksPipelines
StatusCompleted 2023

The project involved laying of approximately 50km of distribution pipeline for two irrigation schemes; the Don Irrigation Scheme which draws water from the Forth River, and the Barrington Irrigation Scheme from Lake Barrington.

The pipeline was constructed with buttwelded 20m lengths of DN560 and smaller HDPE pipe.
The pipeline accessed 123 privately owned properties with 69 property outlets installed.

Installation of the pipeline encountered high production cropping farms, extreme wet weather, hard rock, and water, service and road crossings.

The project was completed in 14 months.

cross