ProjectIntersection upgrade and safety widening Angela Road – Etna Creek Road
LocationAngela Road to Etna Creek Road, Rockhampton QLD
ClientDepartment of Transport and Main Roads
Key worksRoadways
StatusCompleted

The scope of works included widening and reconstruction of 6.1kms of road. Realignment of Greenlakes Road intersection and 640m of new road construction on Dawson Road for realignment of the intersection.

ProjectByron Bay Bypass
LocationByron Bay NSW
ClientByron Shire Council
Key worksRoadways
StatusCompleted

Hazell Bros completed the construction of the town centre bypass to the west of the rail corridor along the Butler Street road reserve in Byron Bay. The Bypass connects the southern and northern ends of the Byron Bay CBD for through-traffic with road corridor approximately 1km long, easing traffic con-gestion within the CBD allowing traffic to flow smoothly.

The scope of works were primarily constructed within the existing developed and undeveloped Butler Street road reserve and consisted of:

Demolition, clearing & grubbing, earthworks including dewatering & soft soil foundation stabilisation, drainage, road pavements and surfacing, kerbing, line marking, concrete medians & roundabout aprons, shared path, signage, fencing, guideposts & bollards, retaining walls, driveways.

ProjectFitzroy Bridge Upgrades
LocationBanana Creek, Callide Creek, Roundstone Creek, and Sandy Creek, QLD
ClientDepartment of Transport and Main Roads
Key worksBridges
StatusCompleted

The scope of works included the demolition of existing timber bridges and construction of 3 new bridge structures and associated roadworks, and the widening of a fourth bridge with approach works.

Banana Creek

Side track construction and replacement of the existing timber bridge at Banana Creek with a 2-span reinforced concrete bridge, with 1km of road widening and upgrades.


Callide Creek

Side track construction and widening of the Callide Creek Bridge structure from 6.7m to 9.2m (between kerbs) and associated approach works, including the reconstruction of the existing pavement with geometric corrections.


Roundstone Creek

Side track construction and replacement of existing timber bridge at Roundstone Creek with a 4-span reinforced concrete bridge structure, flood improvements at the eastern and western overflows adjacent the bridge site as well as an intersection upgrade to Glenmoral Roundstone Rd.


Sandy Creek

Replacement of the existing timber bridge at Sandy Creek with a 3-span reinforced concrete bridge, and associated approach works.

ProjectMount Lindesay Highway – Rosia Road to Stoney Camp Road
LocationPark Ridge South, QLD
ClientDepartment of Transport and Main Roads
Key worksRoadways
StatusCompleted

This project involved widening of a 1.4km section of the high-way from one lane in each direction to two lanes in each di-rection, including associated shoulders, on and off ramp and adjacent bus stop area. Project elements included:

Installation of 38 streetlights (combination of single and double outreach) traffic loops and CCTV cameras

Project Noosaville Landfill Cell Expansion and Cell 1.1 Capping
LocationDoonan, QLD
ClientNoosa Council
Key worksLandfill
StatusCompleted

Characteristics of the works undertaken included, but were not limited to:

Supply and Installation of landscaping, topsoiling, turfing, tree planting and establishment maintenance (13 weeks)

ProjectNorthern Rivers Rail Trail – Murwillumbah to Crabbes Creek Section
LocationMurwillumbah to Crabbes Creek, NSW
ClientTweed Shire Council
Key worksCommunity infrastructure
StatusCompleted

This project incorporated two tunnels (517m long and 50m long), 29 under bridges, multiple culverts and level crossings.

The works included:

Tree/shrub planting and general landscaping

cross