Mount Lindesay Highway – Rosia Road to Stoney Camp Road
Location
Park Ridge South, QLD
Client
Department of Transport and Main Roads
Key works
Roadways
Status
Completed 2020
This project involved widening of a 1.4km section of the high-way from one lane in each direction to two lanes in each di-rection, including associated shoulders, on and off ramp and adjacent bus stop area. Project elements included:
Construction of 1400m3 of concrete lined drains and 1100m of culvert installation of various sizes from 375RCP to 6 cell 1050 RCP across Mount Lindesay Highway
24000m3 of excavation and 15000m3 of embankment works
Construction of two 1200mm by 25m retaining walls and 3000m3 reinforced earth embankment with 800m soil nails and 110m3 of Shotcrete
Placement and compaction of 11500m3 of plant-mixed foam bitumen
7000 tons of AC14 intermediate course and 2200 tons of open graded asphalt surfacing course
Construction of a 583m (1200-1900mm high) split carriage way barrier, two 75m transition barriers and 2000m (1200mm high) single slope barriers
Installation of 38 streetlights (combination of single and double outreach) traffic loops and CCTV cameras