Northern Rivers Rail Trail

ProjectNorthern Rivers Rail Trail – Murwillumbah to Crabbes Creek Section
LocationMurwillumbah to Crabbes Creek, NSW
ClientTweed Shire Council
Key worksCommunity infrastructure
StatusCompleted 2023

This project incorporated two tunnels (517m long and 50m long), 29 under bridges, multiple culverts and level crossings.

The works included:

  • Clearing and grubbing of weeds and vegetation
  • Removal and recycling of existing railway infrastructure
  • Construction of the rail trail pathway including safety signage
  • Demolition of bridges
  • Repair/restoration of bridges
  • Connecting pathways – from rail trail to the Tweed Regional Art Gallery and from the rail trail to Crabbes Creek Village
  • Treatment of tunnels

Tree/shrub planting and general landscaping

cross